APPENDIX B – MONITORING FRAMEWORK
INTRODUCTION
As part of the process of preparing the LDF it will be necessary to identify an effective monitoring framework against which implementation of the LDF strategy and vision can be measured. This in turn will help to identify any changes that need to be made if a particular policy or suite of policies within the LDF are not delivering their intended outcomes.
PERFORMANCE INDICATORS
Indicators will be identified to show how the performance of the Regeneration DPD will be measured. The government identifies the monitoring process as one that will evolve over time as new information becomes available and lessons are learnt. Indicators may as a consequence change or be refined over time to reflect this evolving process. It is not practicable to include an indicator for every policy in the Regeneration DPD or other LDF documents. Where possible policies will be grouped and common indicators identified. A number of the indicators included in the Core Strategy are also applicable to the monitoring of policies contained in the Regeneration DPD. These indicators have not been repeated here.
ANNUAL MONITORING REPORT (AMR)
The AMR will be the principal component in the monitoring framework, bringing together all the necessary information to successfully monitor the implementation of the LDF into one place. It will be published by December each year and will include an assessment of:
- whether policies and related targets or milestones in LDDs have been met or progress is being made towards meeting them or, where they are not being met or not on track to being achieved, the reasons why;
- what impact the policies are having in respect of national, regional and local policy targets and any other targets identified in LDDs;
- whether the policies in the LDD need adjusting or replacing because they are not working as intended;
- whether the policies need changing to reflect changes in national or regional policy; and
- whether policies or proposals need changing, and the actions needed to achieve this.
The targets and indicators needed to monitor implementation of the LDF will be identified within the AMR. This will include indicators for both the Core Strategy and Regeneration DPD.
INDICATOR | TYPE OF INDICATOR | REGENERATION DPD POLICIES | CORE STRATEGY POLICIES | TARGET | EXISTING BASELINE WHERE APPROPRIATE |
SOURCE |
Number of dwellings completed |
Local | REG1 REG2 REG3 REG18 |
CS1 CS2 CS9 |
2004-11 - 400 dwellings 2011-16 - 1,015 dwellings 2016-21 - 1,015 dwellings 2021-23 - 350 dwellings |
Planning applications/ completion certificates | |
Office floorspace completed | Local | REG1 REG2 REG3 |
CS1 CS2 CS7 |
2004-11 - 20,000 sq.m. 2011-16 - 25,000 sq.m. 2016-21 - 15,000 sq.m. 2021-23 - 2,000 sq.m. |
Planning applications/ completion certificates | |
Retail floorspace completed | Local | REG1 REG2 REG3 REG23 |
CS1 CS2 CS13 |
2004-11 - 2,000 sq.m. 2011-16 - 2,000 sq.m. 2016-21 - 1,000 sq.m. 2021-23 - 400 sq.m. |
Planning applications/ completion certificates | |
Retail warehousing | Local | REG1 REG2 REG3 |
CS1 CS2 CS13 |
2004-11 - 9,000 sq.m. 2011-16 - 2016-21 - 2021-23 - |
Planning applications/ completion certificates | |
Leisure floorspace completed | Local | REG1 REG2 REG3 |
CS1 CS2 CS14 |
2004-11 - 20,000 sq.m. 2011-16 - 25,000 sq.m. 2016-21 - 15,000 sq.m. 2021+ - 2,000 sq.m. |
Planning applications/ completion certificates | |
Hotel floorspace completed | Local | REG1 REG2 REG3 |
CS1 CS2 |
2004-11 - 15,000 sq.m. 2011-16 - 15,000 sq.m. 2016-21 - 2021-23 - |
Planning applications/ completion certificates | |
Education floorspace completed | Local | REG1 REG2 REG3 |
CS1 CS2 |
2004-11 - 30,000 sq.m. 2011-16 - 2,000 sq.m. 2016-21 - 2021-23 - |
Planning applications/ completion certificates | |
Greater Hemlington | ||||||
Number of dwellings completed | Local | REG4 REG6 REG7 REG18 |
CS1 CS3 CS9 |
2004-11 - 171 dwellings 2011-16 - 375 dwellings 2016-21 - 375 dwellings |
Planning applications/ completion certificates | |
Amount of employment land developed (B1/B2 and B8 uses) | Local | REG4 REG5 REG6 REG12 |
CS1 CS3 CS7 |
2004-11 - 1.5 ha 2011-16 - 7.5 ha 2016-21 - 6 ha |
Planning applications/ completion certificates | |
Number of dwellings completed in the Gresham/ Jewels Street area | Local | REG8 REG18 |
CS1 CS9 |
2004-11 - 134 dwellings 2011-16 - 375 dwellings 2016-21 - 375 dwellings |
Planning applications/ completion certificates | |
Number of dwellings completed in the Gove Hill area | Local | REG11 REG18 |
CS1 CS9 |
2004-11 - 50 dwellings 2011-16 - 330 dwellings 2016-21 - 110 dwellings |
Planning applications/ completion certificates | |
Competitive business infrastructure | ||||||
Amount of employment land developed | Local | REG5 REG12 REG13 REG14 REG15 REG16 REG17 REG24 REG25 REG26 |
CS1 CS7 |
Riverside Park - 34.58 ha East Middlesbrough Industrial Estate - 4.88 ha Lawson Industrial Estate - 0.33 ha Cargo Fleet - 16.89 ha Letitia - 0.16 ha Coulby Newham - 0.46 ha Hemlington Grange - 15.00 ha Town Centre 8.00 ha |
Planning applications/ completion certificates | |
Revitalising the housing market | ||||||
Number of dwellings completed | Local | REG1 REG4 REG8 REG11 REG18 |
CS1 CS9 |
2004-11 - 5,176 dwellings 2011-16 - 3,292 dwellings 2016-21 - 1,780 dwellings 2021-23 - 450 dwellings |
1,077 dwellings completed between 10/04/04 and 31/03/07 | Planning applications/ completion certificates |
Number of affordable dwellings provided | Local | REG1 REG4 REG8 REG11 REG18 |
CS1 CS9 CS11 |
2004-11 - 212 dwellings 2011-16 - 336 dwellings 2016-21 - 215 dwellings 2021-23 - 50 dwellings |
Planning applications/ completion certificates | |
A 21st Century retail centre | ||||||
Amount of completed retail development | Local | REG20 REG21 REG22 REG23 REG24 REG25 REG26 REG27 REG28 REG29 REG30 |
CS1 CS13 CS14 CS15 |
Convenience floorspace: 2006-16 = 2,800 sq.m. Comparison floorspace: 2006-16 = 41,900 sq.m. |
N/A | Planning applications/ completion certificates |
A regional centre for education, health and culture | ||||||
Provision of high quality health facilities | Local | REG32 REG33 |
CS1 | Development of new facilities at:
|
N/A | Planning applications/ completion certificates |
Connecting Middlesbrough | ||||||
Implementation of transport schemes for East Middlesbrough Corridor | Local | REG34 REG35 |
CS17 | No permitted development that would prejudice the implementation of transport schemes | N/A | Planning applications/ completion certificates |
Provision of new park and ride facilities to serve South Middlesbrough | Local | REG6 |
CS17 | Provision of park and ride facilities in the general locations of Hemlington/A19/A174 junction | N/A | Planning applications/ completion certificates |